Opportunity Awaits.

Different perspectives are what make us successful. Not only will BNA® Vision create the world-class airport experience in Nashville, but it will also provide valuable contracting opportunities for businesses—both large and small—throughout the region.

 

BNA Vision SMWBE Participation By Project

Interim International Arrivals Building (IAB)

PROJECT STATUS: COMPLETE

  • Design and Construction:
    • MBE Participation
      • Goal: 9.35%
      • Achieved: 18.38%
    • WBE Participation
      • Goal: 2.66%
      • Achieved: 1.08%
    • SBE Participation
      • Goal: 4.0%
      • Achieved: 3.07%

Terminal Garage 2 – Parking, Ground Transportation Center

PROJECT STATUS: COMPLETE

  • Design:
    • MBE Participation
      • Goal: 6.07%
      • Achieved: 6.99%
    • WBE Participation
      • Goal: 6.74%
      • Achieved: 6.19%
  • Construction:
    • MBE Participation
      • Goal: 8.33%
      • Achieved: 8.79%
    • WBE Participation
      • Goal: 3.83%
      • Achieved: 9.34%

Terminal Apron and Taxilane Expansion, Phase 1

PROJECT STATUS: PHASE 1 COMPLETE

  • Design:
    • WBE Participation
      • Goal: 11.29%
      • Achieved: 10.93%
  • Construction:

    • DBE Participation
      • Goal: 7.00%
      • Achieved: 7.22%

Concourse D and Terminal Wings Expansion

PROJECT STATUS: COMPLETE

  • Design and Construction:
    • MBE Participation
      • Goal: 6.29%
      • Achieved: 10.37%
    • WBE Participation
      • Goal: 9.13%
      • Achieved: 11.02%
    • SBE Participation
      • Goal: 4.00%
      • Achieved: 7.70%

Participation figures shown above are from contractor’s most recent payment application (August 2021)


Terminal Garage 1 – Parking, Valet, Administrative Building

PROJECT STATUS: COMPLETE

  • Design and Construction:
    • MBE Participation
      • Goal: 8.69%
      • Achieved: 11.95%
    • WBE Participation
      • Goal: 12.62%
      • Achieved: 14.77%
    • SBE Participation
      • Goal: 4.00%
      • Achieved: 4.90%

Participation figures shown above are from contractor’s most recent payment application (November 2021)


Terminal Lobby and International Arrivals Facility

PROJECT STATUS: COMPLETE

  • Design and Construction:
    • MBE Participation
      • Goal: 8.50%
      • Achieved: 2.37%
    • WBE Participation
      • Goal: 11.53%
      • Achieved: 2.26%
    • SBE Participation
      • Goal: 5.00%
      • Achieved: 1.39%

Participation figures shown above are from contractor’s most recent payment application (October 2021)


Terminal Garage 3

PROJECT STATUS: COMPLETE
Design and Construction:

    • MBE Participation
      • Goal: 9.08%
      • Achieved: 0.28%
    • WBE Participation
      • Goal: 13.17%
      • Achieved: 0.62%
    • SBE Participation
      • Goal: 4.00%
      • Achieved: 0.73%

Participation figures shown above are from contractor’s most recent payment application (November 2021)


Terminal Access Roadway Improvements

PROJECT STATUS: IN PROGRESS
Anticipated Project Completion: 2024

  • Design:
    • MBE Participation
      • Goal: 8.01%
      • Achieved: 8.01%
    • WBE Participation
      • Goal: 5.79%
      • Achieved: 7.37%
  • Construction:
    • MBE Participation
      • Goal: 6.10%
      • Achieved: 0.37%
    • WBE Participation
      • Goal: 8.41%
      • Achieved: 3.43%
    • SBE Participation
      • Goal: 4.00%
      • Achieved: 0.31%

Participation figures shown above are from contractor’s most recent payment application (September 2021)


Contracting and procurement opportunities for BNA Vision will be shared on this page as they become available and through the BNA Business Opportunities page.

Additional Resources

2022 Business Taking Off

Click here for the 2022 Business Taking Off presentation

Click here for the 2022 Business Taking Off video

2019 Business Taking Off

Click here for the 2019 Business Taking Off presentation

2018 Business Taking Off

Click here for the 2018 Business Taking Off presentation

2017 BNA Vision Industry Forum

Click here for the 2017 BNA Vision Industry Forum presentation